What it checks
Check the vertical phase relationship where a tap connects between two overhead distribution spans.
Engineering Zone
Calculate conductor sag and required vertical phase framing for a utility distribution midspan tap.
Check the vertical phase relationship where a tap connects between two overhead distribution spans.
Use a known governing sag or calculate sag from horizontal tension and conductor weight, then combine both span profiles with the tap location and attachment geometry.
Use tension, weight, and sag from the same project loading condition. Confirm hardware movement, construction tolerances, and project-specific electrical clearances.
Engineering aid only. Verify the inputs, assumptions, results, and applicable project requirements before use in a final design.